Emergency Repairs to Start on Hwy 30 & 91

BLAIR –  The Nebraska Department of Transportation (NDOT) is currently
working to make repairs to the flood-damaged roadway and bridges on various emergency projects in the Omaha Metro Area. These include:
 Highway 30: Omni Engineering, Omaha, Nebraska, has the existing repair and resurfacingcontract and will perform immediate repairs on Highway 30 between Fremont and Arlington. This work includes a road segment for full reconstruction. Traffic remains detoured while repairs take place. The repair and resurfacing project will continue after the immediate repairs are completed and the highway is open to traffic.
 Highway 77: Thompson Construction, Fremont, Nebraska, has been awarded the contract to start immediate repairs on Highway 77 north of Fremont between US-275 and Logan Creek. This work includes shoulder reconstruction and mainline paving. Traffic is being maintained in a single lane through the use of a pilot car.
 Highway 91: Goree Excavating, Fremont, Nebraska, has been awarded the contract to startvimmediate repairs on Highway 91 between Nickerson and Fontanelle. This work includes a road segment for full reconstruction. Traffic remains detoured while repairs take place.
 Highway L28B (West Dodge Road):  Hawkins Construction, Omaha, Nebraska, has been awarded the contract to start immediate repairs to the section of West Dodge Road between US-275 and 228th Street. This work includes major reconstruction of the 4-lane roadway to restore immediate connectivity. Traffic remains detoured while repairs take place.
Highway US-275: Constructors Inc., Lincoln, Nebraska, has been awarded the contract to start immediate repairs to the section of highway on West Center Road (Highway 275), between the N-92/US-275 junction and the Elkhorn River. This work includes total bridge and pavement replacement. Traffic remains detoured while repairs take place. Motorists are reminded to be aware of marked detours and to plan accordingly. Additionally, motorists are reminded to follow the direction provided by the pilot car and to remain patient on roadways that
remain open while repairs are made.
.
Roadways that remain underwater:
 Highway US-34 from the Highway US-75 junction to the Iowa border.
NDOT will continue to provide detours for each bridge and paving section that has either been washed  out or requires repair through 511.nebraska.gov.